Configure Ventilation at Project Level

Shows step-by-step how to set the ventilation system at the project level.

Before you begin

You would like to configure the ventilation system for your project.

Navigate to

Module OverviewHeat LoadProject LevelGeneral Heat Load Data

Procedure

  1. Select a ventilation system from the drop-down list.
  2. Enter the efficiency of the heat recovery system η Value (HR).
  3. Select the Efficiency Factor Heat Recovery for the efficiency of the heat recovery system.
  4. Disable the checkbox General Calculation q_i (ISSO 51) if you do not want to calculate the specific heat losses due to infiltration using the flat rate method and want to use a measured infiltration quantity.
    The input field Measured Infiltration Quantity (10 Pa) (ISSO 51) is activated.
  5. If necessary, enter the measured infiltration quantity in the field measured infiltration quantity (10 Pa) (ISSO 51).
  6. If the specific air permeability at 10 Pa is known, check the box specific air permeability (10 Pa) known (ISSO 53) and enter the value in the field spec. air permeability (10 Pa) (ISSO 53).
  7. If you would like to get an error message in the ventilation zone in case of an unbalanced air volume balance, activate the option Check air volume balance.

Results

The ventilation at project level is configured.